Turning fleet data into measurable operational value
At Tujuh Bukit Gold Mine in East Java, PT Bumi Suksesindo (BSI), a subsidiary of PT Merdeka Copper Gold Tbk, wanted to achieve greater consistency in fleet productivity across shifts. By combining Hexagon OP Pro fleet management technology with Hexagon Smart Centre consulting, BSI gave its teams greater visibility into fleet activity and the ability to act on inefficiencies as they happened. Within six months, FMS adoption matured significantly, helping reduce idle time, improve productivity and fuel efficiency, lower load and haul costs, and minimise ore loss. The result is a practical example of people, technology, and continuous improvement working together to create measurable operational value.
Combining real-time fleet visibility with operational expertise to turn everyday decisions into measurable improvements
Before implementing OP Pro, dispatch decisions at Tujuh Bukit relied heavily on manual coordination and operator experience. Issues such as truck queuing, fuel waste and ore misrouting could remain hidden until after a shift had ended. OP Pro gives teams real-time visibility into fleet activity, production, and equipment utilisation, allowing them to identify inefficiencies and make better-informed decisions while there is still time to influence the outcome. Incorporating Smart Centre consulting, BSI has also focused on developing the people and processes around the technology, transferring knowledge, embedding best practices and continuously fine-tuning optimisation to reflect changing operating conditions.
From better fleet allocation to lower costs and improved recovery
As adoption of OP Pro matured, BSI began seeing measurable improvements across its operation. Increased use of OP Pro’s Optimiser enabled trucks to be dynamically assigned according to the latest requirements of loading equipment, helping reduce idle time and improve productivity.
Within six months, truck queue time decreased by 17% and excavator hang time by 53%. At the same time, truck productivity increased by 11% and excavator productivity by 17%. These efficiencies contributed to a 14% reduction in load and haul costs.
The benefits extended beyond productivity. BSI achieved a 9.5% reduction in fuel ratio, while reduced idling and unnecessary travel contributed to a reduction of more than 3,400 tonnes of CO₂ emissions annually. High-precision loading guidance also helped minimise ore loss by approximately 600 ounces.
Behind these results is an ongoing focus on people and continuous improvement. Through OP Pro and Smart Centre consulting, BSI has worked to embed knowledge, standardise processes, and build confidence in data-driven decision-making across the operation.
For BSI, fleet optimisation is no longer simply about moving trucks efficiently. It is about moving the right material to the right place at the right time, while reducing waste and creating a more consistent approach to productivity across every shift.